Title
CRA RESOLUTION NO. CRA-25R-11-13: A RESOLUTION OF THE CITY OF LAUDERHILL COMMUNITY REDEVELOPMENT AGENCY (“CRA”) APPROVING A CHANGE ORDER IN THE AMOUNT OF $96,500.00 WITH PLATINUM GENERAL CONTRACTING TO INCORPORATE REQUIRED POLICE SUBSTATION ENHANCEMENTS INTO THE EXISTING SOUTH WING STOREFRONT RENOVATIONS AGREEMENT; PROVIDING FOR PAYMENT FROM THE APPROPRIATE BUDGET CODE NUMBERS; AND PROVIDING FOR AN EFFECTIVE DATE (REQUESTED BY CRA EXECUTIVE DIRECTOR SEAN HENDERSON).
Body
Request Action:
Staff is requesting approval of a change order for Platinum General Contracting to incorporate required Police Substation enhancements into the existing south wing storefront renovations contract. The Police Substation design was finalized after Phase A was bid, resulting in added security and value-added structural elements not included in the original scope.
Need:
Approving this change order is the most efficient and cost-effective path forward.
Summary Explanation/ Background:
Phase A of the project was designed and bid prior to the finalization of the Police substation layout, security features, and material specifications. As the Police Substation design evolved, several mission-critical enhancements became necessary to meet law enforcement operational standards. Key modifications include the installation of Kevlar materials for ballistic protection along with the conversion of specialized wire-mesh wall systems to concrete block which improves strength and long-term durability.
Attachments:
1. Change Order Memo
2. CRA-25R-07-04
3. Platinum General Contracting - Contract
4. Wyngate Plaza Proposal
Cost Summary/ Fiscal Impact:
623-114-6442 Capital Improvement in the amount of $96,500.
Estimated Time for Presentation:
Master Plan:
Goal 1: Clean, Green Sustainable Environment
[ ] Increase mass transit ridership [ ] Reduce City energy consumption
[ ] Reduce water consumption
Goal 2: Safe and Secure City of Lauderhill
[ X ] Crime in lower 50% in Broward [ X ...
Click here for full text