Legislation Details

File #: 26R-6691    Version: 1 Name:
Type: Resolution Status: Passed
File created: 7/1/2026 In control: City Commission Meeting
On agenda: 7/13/2026 Final action:
Title: RESOLUTION NO. 26R-07-117: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF LAUDERHILL, FLORIDA, APPROVING THE FIRST AMENDMENT TO THE CONSTRUCTION AGREEMENT WITH J & D CONCRETE WORKS CORP. FOR ADDITIONAL MILLING AND RESURFACING SERVICES AT VETERAN PARK AND WESTWIND PARK PURSUANT TO BID NO. 2025-041; AUTHORIZING THE CITY MANAGER TO EXECUTE THE FIRST AMENDMENT; FURTHER AUTHORIZING THE CITY MANAGER AND CITY ATTORNEY TO DO ALL THINGS NECESSARY TO EFFECTUATE THIS RESOLUTION; AND PROVIDING FOR AN EFFECTIVE DATE. (REQUESTED BY CITY MANAGER KENNIE HOBBS, JR.).
Attachments: 1. RES 26R-07-117 approving amendment to J D Construciton Contract, 2. AR 26R-07-117, 3. Construction Agreement - JD Concrete Works Corp, 4. 26-091 Veteran Park Milling and Resurfacing - Estimate R2, 5. 26-092 Westwind Park Milling and Resurfacing - Estimate R1, 6. J & D Amendment version.docx 6-22-26
Title
RESOLUTION NO. 26R-07-117: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF LAUDERHILL, FLORIDA, APPROVING THE FIRST AMENDMENT TO THE CONSTRUCTION AGREEMENT WITH J & D CONCRETE WORKS CORP. FOR ADDITIONAL MILLING AND RESURFACING SERVICES AT VETERAN PARK AND WESTWIND PARK PURSUANT TO BID NO. 2025-041; AUTHORIZING THE CITY MANAGER TO EXECUTE THE FIRST AMENDMENT; FURTHER AUTHORIZING THE CITY MANAGER AND CITY ATTORNEY TO DO ALL THINGS NECESSARY TO EFFECTUATE THIS RESOLUTION; AND PROVIDING FOR AN EFFECTIVE DATE. (REQUESTED BY CITY MANAGER KENNIE HOBBS, JR.).

Body
Request Action:

Approval of a first amendment to the Construction Agreement between the City of Lauderhill and J & D Concrete Works Corp. to add milling and resurfacing improvements at Veteran Park and Westwind Park under the City's existing contract for Milling and Resurfacing Services (BID No. 2025-041).

Need Summary Explanation/ Background:

On October 7, 2025, the City entered into a Construction Agreement with J & D Concrete Works Corp., for Milling and Resurfacing Services pursuant to BID No. 2025-041. The original contract amount was $641,870.78.
The Construction Department has identified additional locations requiring milling and resurfacing improvements that fall within the scope of the existing contract. J & D Concrete Works Corp., submitted the following proposals:
? Veteran Park Milling and Resurfacing - Proposal No. JD 26-091 R2 dated April 14, 2026, in the amount of $85,117.19.
? Westwind Park Milling and Resurfacing - Proposal No. JD 26-092 R1 dated April 14, 2026, in the amount of $75,112.15.
The proposed amendment incorporates these additional locations into the existing agreement and increases the contract by $160,229.34, resulting in a revised contract amount of $802,100.12. All other terms and conditions of the original agreement remain unchanged.

Cost Summary/ Fiscal Impact:

The amendment increases the contract amount by $160,...

Click here for full text