Legislation Details

File #: 26R-6687    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/30/2026 In control: City Commission Meeting
On agenda: 7/13/2026 Final action:
Title: RESOLUTION NO. 26R-07-118: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF LAUDERHILL, FLORIDA, APPROVING AMENDMENT NO. 1 TO THE AGREEMENT WITH INLINER SOLUTIONS, LLC, FOR THE CDBG-MIT MT049 SEWER LINING REPLACEMENT AND REHABILITATION PROJECT; APPROVING AN INCREASE TO CPH’S PURCHASE ORDER FOR SUPPORT SERVICES; AUTHORIZING THE CITY MANAGER TO EXECUTE THE AMENDMENT AND ALL RELATED DOCUMENTS; AUTHORIZING THE CITY MANAGER AND CITY ATTORNEY TO DO ALL THINGS NECESSARY TO EFFECTUATE THIS RESOLUTION; AND PROVIDING FOR AN EFFECTIVE DATE (REQUESTED BY CITY MANAGER KENNIE HOBBS, JR.).
Attachments: 1. RES 26R-07-118 approving Inliner change order, 2. AR 26R-07-118, 3. 1.City Amendment Request 06.02.2026_R2, 4. 2. AIA Change Order 05.27.2026 (004), 5. 3. MT049 AMENDMENT#2_READY FOR SIGNATURE, 6. 4. INLINER -Equitable Price Adjustment Request, 7. 5. INLINER Construction LS6-9 Estimate 06.05.2026 R2, 8. 6. CONSULTANT - CPH Cost Proposal for Extension $78,880, 9. 7. CDBG-MIT (MT049)- Sewer Lining Financial Status & Budget Mod, 10. 8. RES 24R-06-106 Bid RFP 2024-025 Sewer Lining Services

Title

RESOLUTION NO. 26R-07-118: A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF LAUDERHILL, FLORIDA, APPROVING AMENDMENT NO. 1 TO THE AGREEMENT WITH INLINER SOLUTIONS, LLC, FOR THE CDBG-MIT MT049 SEWER LINING REPLACEMENT AND REHABILITATION PROJECT; APPROVING AN INCREASE TO CPH’S PURCHASE ORDER FOR SUPPORT SERVICES; AUTHORIZING THE CITY MANAGER TO EXECUTE THE AMENDMENT AND ALL RELATED DOCUMENTS; AUTHORIZING THE CITY MANAGER AND CITY ATTORNEY TO DO ALL THINGS NECESSARY TO EFFECTUATE THIS RESOLUTION; AND PROVIDING FOR AN EFFECTIVE DATE (REQUESTED BY CITY MANAGER KENNIE HOBBS, JR.).

 

Body

Request Action:

 

A Resolution of the City Commission of the City of Lauderhill approving Amendment No. 1 to the Agreement with Inliner Solutions, LLC, for the Community Development Block Grant - Mitigation (CDBG-MIT) MT049 Sewer Lining Replacement and Rehabilitation Project; authorizing the City Manager to execute the Amendment and all related documents; providing for an effective date.

 

Need Summary Explanation/ Background:

On June 10, 2024, the City Commission approved Resolution No. 24R-06-106 awarding Bid No. 2024-025 to Inliner Solutions, LLC in an amount not to exceed $2,971,775.00 for sewer lining services associated with the City's wastewater collection system. The project is funded through the Florida Department of Commerce Community Development Block Grant-Mitigation (CDBG-MIT) Program under Agreement No. MT049.

During construction, CCTV inspections and field investigations determined that a substantial portion of the sewer mains originally scheduled for rehabilitation had previously been lined, resulting in available construction funding within the grant budget. The City proposes utilizing these available funds to expand the project and maximize the benefit of the grant. The reallocated funds will be utilized for Project Implementation services necessary to support project management, construction administration, grant compliance, coordination, documentation, and oversight associated with the expanded scope of work and extended project duration.

Cost Summary/ Fiscal Impact:

 

Amendment No. 1 provides for the following:

                     Expands the project scope to include rehabilitation within four (4) additional lift station service areas identified through field investigations.

                     Extends the construction contract by 365 calendar days, establishing a new substantial completion date of March 5, 2027.

                     Reduces the construction allocation from $2,971,775.00 to $2,901,775.00, reallocating $70,000.00 to Project Implementation services necessary for grant administration, construction oversight, compliance, and project closeout.

                     Increasing the Consultant, CPH Consultant, PO# 26700/29312 by $78,880.00

                     Revises the Schedule of Values and unit prices applicable only to the additional work to reflect current market conditions, including an 8% equitable price adjustment for the newly added work. The original contract unit prices remain unchanged for the original scope of work.The amendment allows the City to maximize the use of available CDBG-MIT funding while completing additional eligible wastewater infrastructure improvements without increasing the overall grant award of $3,125,215.00.

 

 

There is no increase to the overall CDBG-MIT grant award. Funding remains within the total grant budget of $3,125,215.00. The amendment reallocates $70,000.00 from the construction budget to project implementation services and revises the construction budget to $2,901,775.00. All costs are funded through the existing CDBG-MIT Grant Agreement MT049.

 

Attachments:

1.                     Resolution

2.                     City Amendment Request 06.02.2026_R2

3.                     AIA Change Order Form

4.                     MT049 Amendment#2 to DEO Agreement, Pending CM Signature. 

5.                     Inliner Price Adjustment Request. 

6.                     Inliner LS6-9 Cost Estimate with Price Adjustment Rate.

7.                     Consultant - CPH Cost Proposal for extension

8.                     MT049 Sewer Lining Financial Status & Budget Modification.

9.                     RES 24R-06-106 Construction Bid for Sewer Lining  

 

Budget Code Number(s): Funded through the existing CDBG-MIT Grant Agreement MT049

 

Procurement Information: [check all that apply]

[    ] RFP/Bid                                                               [    ] Emergency Purchase                                           [    ] SBE

[    ] Proposal/Quote                                          [  X ] State Grant Funds                                          [    ] Local Preference

[    ] Piggyback Contract                     [   ] Federal Grant Funds                                         

[    ] Sole Source                                          [   ] Matching Required